The latest building control Gateway 2 update from the Building Safety Regulator (BSR) shows a continuing de-gumming of this new and complex process.
In the 12 weeks to 30 May, approval rates increased across all application categories, including existing building safety projects, after BSR introduced an external remediation improvement plan in April.
The plan introduced a multidisciplinary team to mirror the Innovation Unit (IU) set up last September. This streamlines communication and processing through dedicated account managers.